Know Before You Go: Traffic Disruptions - July 24 to July 30
July 24, 2026

The 2026 construction season is well underway across Edmonton. To help travellers plan their routes, the City is sharing timely information through social media and the Traffic Disruptions Map.

Once complete, these transportation projects will improve how people move through the city, whether walking, rolling, driving or taking transit.

Please note, construction schedules may change due to weather, underground conditions and other project dependencies. The City works to provide the most accurate timing available and appreciates everyone’s patience should schedules change.

Traffic impacts
  • Dawson Bridge Rehabilitation
    • Dawson Bridge has reopened to two lanes of traffic following the single-lane closure in July, however, the bridge will be fully closed from Wednesday, July 29 to Saturday, August 1 to complete work rescheduled due to weather. 
  • High Level Bridge West Sidewalk
    • The High Level Bridge west sidewalk and the 97 Avenue bridge approach have reopened to pedestrians, cyclists and vehicles.
      The City thanks everyone for their patience while crews completed repairs to the slope. 
  • 95 Avenue Renewal
    • The northbound curb lane on 170 Street just before 95 Avenue will be closed periodically during off-peak hours over the next month. Please follow posted signage.
  • Imagine Jasper Avenue
    • Starting Thursday, July 30, traffic on Jasper Avenue between 119 Street and 121 Street will be redirected to the new road surface on the north side of the avenue while work begins on the south side.
  • Victoria Park Road Bike Lane
    • Construction to complete the permanent protected two-way bike lane along Victoria Park Road will continue until July 31, weather permitting. Cyclists and pedestrians should be prepared for intermittent bike lane closures. Pedestrian access will be maintained, and cyclists will be asked to dismount and walk their bikes through the work area.
  • Valley Line West LRT
    • Track and rail installation on the Anthony Henday Drive northbound on/off ramp at 87 Avenue has been rescheduled to this weekend after being postponed earlier this month. The work will take place overnight from 9 p.m. to 5 a.m., July 23 to 26. The ramp will be closed during this time.
    • On July 24, streetlight and traffic signal poles will be installed on Stony Plain Road between 149 Street and 146 Street from 9 p.m. to 6 a.m. Eastbound traffic will be detoured at 149 Street to 107 Street. Drivers can use 142 Street to access Stony Plain Road. This work is expected to take one night.
    • Utility work on 87 Avenue near 189 Street, originally scheduled for July 17, has been rescheduled to July 24. The work will take place in the westbound lane and is expected to last one night. While work is underway, westbound through traffic and the left-turn lane will share one lane near 189 Street.
    • On or around July 28, crews will begin installing streetlight and traffic signal poles on Stony Plain Road between 149 Street and 156 Street. Westbound traffic will be detoured around the work site. The work will take place Monday to Friday from 9 a.m. to 3 p.m. and is expected to last approximately one week.
    • Drainage and roadwork on the north side of 87 Avenue between 182 Street and 189 Street has been extended by one month due to heavy rainfall. Work began mid-May and was originally expected to take two months. Access to and from 87 Avenue from the north side of 189 Street remains closed.
Traffic Disruptions Map
These projects are being coordinated to complete the work as quickly as possible. For updates on construction impacts and road closures, visit the Traffic Disruptions Map.

The City recognizes construction and temporary detours can cause delays. These projects support long-term infrastructure improvements that will make Edmonton’s transportation network more accessible, connected and reliable for years to come.

For more information, visit
edmonton.ca and search by project name, or contact 311.
For more information: