Temporary full closure of 97 Street for Chinatown Gate construction |
August 20, 2026
Starting on or around Monday, August 24, 97 Street will be temporarily fully closed to vehicle traffic between Jasper Avenue and Okîsikow (Angel) Way (101A Avenue) for approximately two weeks to accommodate construction of the new Chinatown Gate.
Following the reopening of 99 Street/103A Avenue and Okîsikow (Angel) Way, crews are preparing to install the steel structure of the new Chinatown Gate along 97 Street. Key components have been preassembled to speed up installation and significantly reduce the number of nighttime closures required afterward.
Drivers are encouraged to use 100 Street or 95 Street as main detours via Jasper Avenue or 103A Avenue. During the temporary full closure, southbound drivers on 97 Street will be permitted to turn left onto eastbound 103A Avenue. This turn is currently prohibited but will be temporarily allowed to help reduce traffic congestion in the area.
Vehicle access will be maintained on 97 Street between 102A Avenue and Okîsikow (Angel) Way, including access to the Canada Place parkade on the west side of 97 Street, north of Okîsikow (Angel) Way.
Pedestrian access will be maintained on both sides of 97 Street.
Construction will take place during daytime hours Monday through Sunday throughout the closure.
Following the two-week full closure, the same section of 97 Street will close overnight for approximately two additional weeks, around September 8 to 21. The closures will take place from 8 p.m. to 6 a.m. seven days a week to allow crews to install scaffolding and hoarding.
In late September, one northbound lane on 97 Street will be closed during daytime, off-peak hours for approximately three weeks to allow for material delivery.
ETS Routes 111, 130X, 150X and 900X, as well as St. Albert Transit Route 211 will be detoured. Visit edmonton.ca/TransitAlerts for a full list of closed and alternate stops.
See the construction notice for more information and a map. For updates on construction impacts and road closures, visit the Traffic Disruptions Map.
Construction of the new gate began in March and is expected to be completed in 2027. |
For more information:
Media contact:
Caley Gibson
Communications Advisor
Infrastructure Services
780-217-5030
|
City of Edmonton Edmonton Tower, 10111 104 Avenue, Edmonton, T5J 0J4 Unsubscribe |
|
|
|