Know Before You Go: Traffic Disruptions - September 18 to September 24 |
September 18, 2026
The 2026 construction season is in full swing across Edmonton. To help travellers plan their routes, the City is sharing timely information through social media and the Traffic Disruptions Map.
Once complete, these transformational projects will improve how people move through the city, whether walking, rolling, driving or taking transit.
Please note, construction schedules may change due to weather, underground conditions and other project dependencies. The City works to provide the most accurate timing available and appreciates everyone’s patience should schedules change.
Traffic impacts
- Imagine Jasper Avenue
- 117 Street, 118 Street and 119 Street south of Jasper Avenue are closed until the end of October to accelerate construction.
- Traffic on Jasper Avenue will remain open with one lane in each direction.
Traffic on Jasper Avenue is shifting to the north side of the road from east of 116 Street to west of 117 Street on September 20 until construction on the south side of Jasper Avenue is completed in 2026. The traffic shift allows 117 Street and 118 Street north of Jasper Avenue to reopen to two lanes of traffic.
- Access to Bubbles Car Wash is available from the alley north of Jasper Avenue until September 20. Starting September 21, access will be available from Jasper Avenue.
- Terwillegar Stage 2
- Starting today until October 2, Whitemud Drive will be reduced to one lane in each direction between 53 Avenue and 122 Street nightly from 9 p.m. to 6 a.m. on weekdays and until 9 a.m. on weekends.
- The Terwillegar Drive on- and off-ramps will be closed on select nights as required.
- From September 28 to October 1, full closures of Whitemud Drive will take place between 2 a.m. and 4 a.m. for up to 30 minutes at a time while overhead signs are installed.
- Chinatown Gate
- Overnight closures of 97 Street between Jasper Avenue and Okîsikow (Angel) Way (101A Avenue) will continue until approximately September 28. Closures will take place from 8 p.m. to 6 a.m. seven days a week to allow crews to install scaffolding and hoarding. Drivers are encouraged to use 100 Street or 95 Street as detour routes via Jasper Avenue or 103A Avenue.
- 112 Avenue Bridge Over Wayne Gretzky Drive Rehabilitation
- The 112 Avenue Bridge over Wayne Gretzky Drive will be closed nightly until September 20 while crews replace bearings and remove temporary shoring. Closures will be in place from 10 p.m. to 6 a.m., except on September 18 and 19, when they will begin at 11 p.m. to accommodate traffic from the Kaleido Festival.
- Overnight closures will resume from September 22 to September 24.
- Traffic on Wayne Gretzky Drive will not be affected.
- Capital Line South
- Beginning on or around September 19, a lane reconfiguration will occur at the intersection of 111 Street and 23 Avenue, shifting traffic toward the northwest corner. All through lanes and turning movements at the intersection will remain open. This traffic configuration is expected to remain in place until late October or early November.
- Starting on or around September 21, 111 Street near Century Park Station will be reduced to one southbound lane for approximately two weeks to complete drainage work. Northbound traffic will not be affected.
- Valley Line West LRT
- Median construction at the southeast corner of Stony Plain Road and 142 Street, originally scheduled to begin earlier this month, has been rescheduled to begin on or around September 21. The outside northbound through lane on 142 Street will be closed. All other lanes and turning movements will remain open. This work is expected to take approximately one week.
- High Level Bridge
- Starting on or around Monday, September 21, EPCOR will conduct drainage work on the bridge for approximately nine weeks. The west entrance to the bridge from 97 Avenue will be temporarily closed to traffic. The west lane across the bridge will remain open, and traffic entering from the east will continue to have access to both lanes. The west sidewalk is expected to remain open for pedestrians and cyclists, with temporary overnight closures as needed.
Traffic Disruptions Map
These projects are being coordinated to complete the work as quickly as possible. For updates on construction impacts and road closures, visit the Traffic Disruptions Map.
The City recognizes construction and temporary detours can cause delays. These projects support long-term infrastructure improvements that will make Edmonton’s transportation network more accessible, connected and reliable for years to come.
For more information, visit edmonton.ca and search by project name, or contact 311.
|