PROJECT UPDATE
Taylors Ferry Reservoirs and Site Seismic Improvement Project: September 2026 |
Dear Valued Customers and Community Members,
Here’s the September 2026 update for the Taylors Ferry Reservoirs and Site Seismic Improvement Project, including a look ahead at work planned for the final few months.
Once complete, the Taylors Ferry site will include two new reservoirs, a pump station, an operations building, and new pipelines. These facilities will work with the nearby Florence Lane and Garden Home reservoirs to store and deliver drinking water to customers in the Metzger area.
The water will come from the new Willamette Water Supply System, which will draw water from the Willamette River near Wilsonville.
September Progress
Crews made significant progress on the new pump station and operations building and began work on the site's stormwater detention area. Work also continued on slope restoration and landscaping.
Pump Station
Crews continued construction of the new pump station, including placement of below-grade electrical conduit, water piping, and plumbing followed by placement of the concrete footings and stem walls. Crews also prepared the foundation area for the emergency generator, which will provide backup power to the pump station if normal electrical service is interrupted.
The station will house four pumps: two for normal service and two for high flows. Each high-flow pump will be capable of delivering up to 1,500 gallons of water per minute. Together, the pumps will move drinking water through the system and into the distribution system serving nearby customers.
Operations Building
Work continued on the new operations building on the north side of the new reservoirs. The building will provide space for equipment storage and other activities needed to operate and maintain the Taylors Ferry facilities.
September work included:
- Completing interior wood framing, insulation, and drywall installation.
- Completing installation of the roofing system and roof drains.
- Completing interior and exterior painting.
- Measuring and building cabinets for kitchenette area.
- Completing rough-in of electrical and plumbing
Stormwater Detention Area
Crews began work on the stormwater detention area between the new operations building and pump station, including installation of stormwater piping.
The detention area will temporarily hold rainwater runoff during and after storms, allowing it to be released gradually. This helps manage runoff from the Taylors Ferry property and reduce the potential for erosion or impacts to nearby drainage systems.
Slope Restoration and Landscaping
Crews completed restoration on the north slope of the Taylors Ferry property. Work included grading the hillside to restore its shape and stability, applying erosion-control materials, hydroseeding, and adding plants.
These improvements will help protect the slope from erosion and restore vegetation in areas disturbed during construction.
See the photos below for a closer look at the project’s progress.
What’s Next
Over the next couple months, crews will complete the construction of the pump station, operations building, stormwater facilities, and other site improvements. Substantial completion – including startup of the new pump station – is now expected in December 2026. The contractor will remain on site through early 2027 to complete minor construction activities and final site work.
Upcoming work includes:
- Landscaping in the new stormwater detention area.
- Removing the existing fence around the property and installing new fencing.
- Installing bollards to help protect equipment and facility structures from vehicle impacts.
- Constructing the new pump station’s building concrete floor, installing underground electrical utilities, and completing wood framing, roof trusses, and concrete masonry unit (CMU) walls for the pump station.
- Installing cabinets and completing remaining interior work in the operations building.
Crews will also continue inspections, testing, site cleanup, landscaping, and other work needed to prepare the new facilities for operation.
What to Expect
No project-related water service interruptions are planned for nearby customers during October.
Neighbors near the construction site may notice:
- Sight: Large equipment, construction vehicles, and continued site cleanup.
- Sound: Construction noise from heavy equipment and backup alarms.
- Smell: Dust and diesel exhaust.
- Feel: Occasional ground vibrations during construction activities.
- Parking: Construction crews may park on nearby public streets in accordance with city regulations.
- Deliveries and services: Mail, package deliveries, and garbage collection will continue, although minor delays are possible.
- Drone use: A drone may be used to take photos and video to document construction progress.
Grand Opening in 2027
TVWD looks forward to celebrating this major investment in your community. A Grand Opening event for the new reservoirs, pump station, and operations building will be held in 2027 following construction and project completion.
Nearby customers and community partners will be invited to tour the facilities and learn more about how this project will strengthen water system resilience, connect the area to a reliable regional water supply, and help maintain consistent water pressure for customers.
Event details will be shared by mail, email, and on the project webpage.
Questions?
Contact TVWD’s Communication Team:
Thank you for your patience and understanding as we work to complete this important project. We appreciate our customers and neighbors as construction continues toward completion.
|
Photo: Aerial view of the Taylors Ferry project site looking north - Sept. 23, 2026. |
|
|
Photo: Aerial view of the Taylors Ferry project site looking south - Sept. 23, 2026. |
|
|
Photo: Looking north toward SW Florence Lane at the stormwater detention area. The area will temporarily collect rainwater runoff from the pump station and reservoir property and release it at a controlled rate. |
|
|
Photo: The new operations building features durable CMU walls and a metal roof designed to provide long-lasting protection for equipment and materials with relatively low maintenance. |
|
|
Photo: Crews install underground conduit that will provide protected pathways for the electrical, communication, and control wiring needed to operate and monitor the new pump station. |
|
|
Photo: Crews construct the new pump station’s below-ground foundation and install large water pipes that will connect the facility to the water system. Reinforcing steel is being installed in the concrete walls to provide structural strength. |
|
|
Coming Soon!
The Willamette Water Supply System will provide additional water to Washington County in mid-2027 so we are better prepared for current and future water challenges. Visit TVWD.org/WWSS to learn what our new water supply means for you. |
|
|
|
|
|
|