Know Before You Go: Traffic Disruptions - November 13 to November 19
November 13, 2026

As the fall season progresses, City crews continue to work across Edmonton. To help travellers plan their routes, the City is sharing timely information through social media and the
Traffic Disruptions Map.

Once complete, these transformational projects will improve how people move through the city, whether walking, rolling, driving or taking transit.

Please note, construction schedules may change due to weather, underground conditions and other project dependencies. The City works to provide the most accurate timing available and appreciates everyone’s patience should schedules change.

This is the final weekly traffic PSA for 2026. Some construction projects will continue through the winter months, weather permitting.
Traffic impacts
  • Imagine Jasper Avenue
    • Year 2 of the Imagine Jasper Avenue project is nearing completion. 
      • Today, the 117 Street and 118 Street intersections have reopened to traffic. 
      • Until Friday, November 20, both northbound and southbound curb lanes will be closed.
      • From November 21 to 27, only the southbound curb lanes will remain closed.
      • 117 Street to 121 Street is expected to fully reopen to all lanes of traffic by the end of November. 
  • Yellowhead Trail Freeway Conversion
    • Yellowhead Trail will be reduced to one lane in each direction from 124 Street to west of 127 Street from today until Sunday, November 15 between 8 p.m. – 6 a.m. for bridge work.
  • Terwillegar Stage 3
    • Windemere Boulevard/Terwilligar Drive
      • Paving on the east side for northbound lanes will be ongoing over the weekend. This work will be complete by Sunday, November 15. Permanent line markings to follow shortly.
      • Crews continue to install new traffic signal bases, street lights and fixtures. Lighting upgrades will continue over the next month as weather permits. In the meantime, existing and temporary lighting remains in place.
    • Terwilligar Drive/Anthony Henday Drive
      • Eastbound Anthony Henday Drive off- and on-ramps will have the first lift paved to accommodate a winter shutdown. 
      • The westbound Anthony Henday Drive off ramp to Terwilligar Drive is being paved today. This will accommodate a winter shutdown.  
      • Line markings will be painted during the week of November 16.
    • Bridges
      • Shared-use path (SUP) bridge: Girder installation will take place overnight (10 p.m. to 6 a.m.) Monday, November 16, and Tuesday, November 17. Traffic will be routed around the work area using newly constructed crossovers. 
      • Main traffic bridge: Overnight girder installation will take place on Thursday, November 19, and Friday, November 20, as well as Monday, November 23, and Tuesday, November 24. During this work, traffic will be detoured up and over the interchange, with Edmonton Police Service (EPS) on site to help direct traffic. 
  • 132 Avenue Collector Renewal
    • Work on 132 Avenue from 121 Street to 127 Street is now complete, marking the completion of the west portion of the 132 Avenue Collector Renewal Project. This section is now open to the public.
    • For the east portion of the project, 132 Avenue between 82 Street and 91 Street is expected to open Saturday, November 14. Construction on the final phase of the east portion, from 91 Street to 97 Street, is expected to be completed next year. 
  • Duggan Bridge Repairs 
    • Temporary overnight closures of Saskatchewan Drive from 106 Street to 107 Street and Fort Hill Road between 87 Avenue and Walterdale Hill will be in place Tuesday, November 17 to Thursday, November 19, from 10 p.m. to 6 a.m. No vehicles or pedestrians will be able to cross the bridge during this time.
      • Following this repair work, additional improvements will be completed on the bridge abutments to help prevent future damage. This work will take place through late December. Fort Hill Road between 87 Avenue and Walterdale Hill will be partially closed during this time, with one lane of traffic maintained. 
  • Valley Line West LRT
    • Work is underway to reopen 87 Avenue to two lanes in each direction between Anthony Henday Drive and 159 Street for the winter. This reconfiguration is expected to take crews several weeks to implement, weather permitting. This traffic pattern is expected to be in place until spring 2027. All intersections along 87 Avenue, including the major intersections at 178 Street and 170 Street, will reopen to full capacity throughout the winter.
    • On or around Monday, November 16, overnight work is scheduled to begin to pull rail across 92 Avenue at 156 Street. Access across 156 Street at 92 Avenue will be closed nightly from 9 p.m. to 5 a.m. Vehicle access will be maintained at the Y-intersection near Meadowlark Road and 156 Street and at 95 Avenue. This work is expected to take approximately one week.
    • On or around Wednesday, November 18, overnight work is scheduled to begin to pull rail across the intersection of Meadowlark Road and 156 Street. Access across Meadowlark Road at 156 Street south will be closed nightly from 9 p.m. to 5 a.m. This work is expected to take approximately one week. Note: Only one intersection will be closed at any given time while the rail installation work in this area takes place.
  • Capital Line South LRT Extension
    • Beginning on or around Saturday, November 14, weather permitting, Ledcor will reconfigure lanes at the intersection of 111 Street and 23 Avenue. This lane shift will change 23 Avenue from a curved roadway to a straight alignment. 111 Street will remain in its current position. All through lanes and turning movements at the intersection will remain open. This traffic configuration is anticipated to remain in place until summer 2027.
    • Beginning on or around Friday, November 13, weather permitting, Ledcor anticipates reopening an additional southbound lane on 111 Street between 12 Avenue and 9 Avenue.
Traffic Disruptions Map
For ongoing updates on construction impacts and road closures, visit the Traffic Disruptions Map.

The City recognizes construction and temporary detours can cause delays. These projects support long-term infrastructure improvements that will make Edmonton’s transportation network more accessible, connected and reliable for years to come.

For more information, visit
edmonton.ca and search by project name or contact 311. 
For more information:

Media contact:
Sheila Keenan
Senior Communications Advisor
Infrastructure Services

City of Edmonton

Edmonton Tower, 10111 104 Avenue, Edmonton, T5J 0J4

Unsubscribe - Unsubscribe Preferences